PGMP · Question #359

The team on the router and switch upgrade project is involved in planning the project. They are performing Risk Response Planning. They are assigning risk owners. What is the main responsibility of…

The correct answer is D. Implementing a risk response plan if the risk event occurs. A risk owner's primary responsibility is to implement the agreed-upon risk response plan if the assigned risk event actually occurs.

Program Risk Management

Question

The team on the router and switch upgrade project is involved in planning the project. They are performing Risk Response Planning. They are assigning risk owners. What is the main responsibility of the risk owner?

Options

  • AWatching for additional risks on the project
  • BWatching for risk triggers and telling the Project Manager if they happen
  • CLetting the Project Manager know that the risk has happened
  • DImplementing a risk response plan if the risk event occurs

How the community answered

(54 responses)
  • A
    2% (1)
  • B
    7% (4)
  • C
    4% (2)
  • D
    87% (47)

Why each option

A risk owner's primary responsibility is to implement the agreed-upon risk response plan if the assigned risk event actually occurs.

AWatching for additional risks on the project

Watching for additional risks is a broader team and Project Manager responsibility, not the specific role of an assigned risk owner.

BWatching for risk triggers and telling the Project Manager if they happen

Watching for risk triggers and notifying the Project Manager describes a monitoring role, which is secondary to the primary responsibility of implementing the response plan.

CLetting the Project Manager know that the risk has happened

Simply notifying the Project Manager that a risk has happened is insufficient; the risk owner is responsible for taking action, not just reporting.

DImplementing a risk response plan if the risk event occursCorrect

The risk owner is the individual assigned accountability for ensuring that a specific risk response plan is executed if the risk event occurs. This includes managing all aspects of that response - coordinating resources, executing the planned actions, and reporting outcomes to the Project Manager. Ownership means being prepared and responsible for action, not just observation or communication.

Concept tested: Risk owner responsibilities in Risk Response Planning

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok

Topics

#Risk Management#Risk Owner#Risk Response Planning#Program Management Roles