PMIPMI
PGMP · Question #359
PGMP Question #359: Real Exam Question with Answer & Explanation
Sign in or unlock PGMP to reveal the answer and full explanation for question #359. The question stem and answer options stay visible for context.
Program Risk Management
Question
The team on the router and switch upgrade project is involved in planning the project. They are performing Risk Response Planning. They are assigning risk owners. What is the main responsibility of the risk owner?
Options
- AWatching for additional risks on the project
- BWatching for risk triggers and telling the Project Manager if they happen
- CLetting the Project Manager know that the risk has happened
- DImplementing a risk response plan if the risk event occurs
Unlock PGMP to see the answer
You've previewed enough free PGMP questions. Unlock PGMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Risk Management#Risk Owner#Risk Response Planning#Program Management Roles