Program Risk Management
Question
The Project Manager and team are planning the project. They are presently identifying things that could go differently than planned. They are also trying to identify warning signs that would show that these events could be on the verge of occurring. What is the team doing?
Options
- ARisk analysis
- BRisk Identification
- CConformance to quality
- DProblem solving
Unlock PGMP to see the answer