nerdexam
PMIPMI

PGMP · Question #349

PGMP Question #349: Real Exam Question with Answer & Explanation

Sign in or unlock PGMP to reveal the answer and full explanation for question #349. The question stem and answer options stay visible for context.

Program Risk Management

Question

The Project Manager and team are planning the project. They are presently identifying things that could go differently than planned. They are also trying to identify warning signs that would show that these events could be on the verge of occurring. What is the team doing?

Options

  • ARisk analysis
  • BRisk Identification
  • CConformance to quality
  • DProblem solving

Unlock PGMP to see the answer

You've previewed enough free PGMP questions. Unlock PGMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Risk Management#Risk Identification#Program Planning#Risk Triggers
Full PGMP PracticeBrowse All PGMP Questions