PGMP · Question #184
What is the other name for critical delivery dates?
The correct answer is D. Milestones.. Milestones are significant, predefined points in a program or project schedule that mark the completion of a major deliverable, phase, or event. They represent zero-duration checkpoints on the schedule and are commonly used to signify critical delivery dates - dates by which some
Question
What is the other name for critical delivery dates?
Options
- ASubstantial completion.
- BPhases
- CFlags.
- DMilestones.
How the community answered
(25 responses)- B4% (1)
- C4% (1)
- D92% (23)
Explanation
Milestones are significant, predefined points in a program or project schedule that mark the completion of a major deliverable, phase, or event. They represent zero-duration checkpoints on the schedule and are commonly used to signify critical delivery dates - dates by which something key must be accomplished. Phases (B) are periods of work, not specific dates. Flags (C) and Substantial completion (A) are not standard scheduling terms for critical delivery dates in the PMI framework.
Topics
Community Discussion
No community discussion yet for this question.