PGMP · Question #184

What is the other name for critical delivery dates?

The correct answer is D. Milestones.. Milestones are significant, predefined points in a program or project schedule that mark the completion of a major deliverable, phase, or event. They represent zero-duration checkpoints on the schedule and are commonly used to signify critical delivery dates - dates by which some

Program Life Cycle Management

Question

What is the other name for critical delivery dates?

Options

  • ASubstantial completion.
  • BPhases
  • CFlags.
  • DMilestones.

How the community answered

(25 responses)
  • B
    4% (1)
  • C
    4% (1)
  • D
    92% (23)

Explanation

Milestones are significant, predefined points in a program or project schedule that mark the completion of a major deliverable, phase, or event. They represent zero-duration checkpoints on the schedule and are commonly used to signify critical delivery dates - dates by which something key must be accomplished. Phases (B) are periods of work, not specific dates. Flags (C) and Substantial completion (A) are not standard scheduling terms for critical delivery dates in the PMI framework.

Topics

#Program Schedule Management#Milestones#Critical Dates#Program Planning