PGMP · Question #483
A country is in the process of strengthening its defense program. A key project is not meeting its specified performance objectives. The project manager initiates a change request to address this issu
The correct answer is C. Assess the benefits and impact to the program. When a component project fails to meet its performance objectives, the program manager's first responsibility is to assess the impact on the overall program's benefits delivery. A change request from a project manager signals a potential ripple effect upward. Before deciding to c
Question
A country is in the process of strengthening its defense program. A key project is not meeting its specified performance objectives. The project manager initiates a change request to address this issue. What should the program manager do NEXT?
Options
- AConsider the option to close out the key project
- BEvaluate the program and re-baseline the objectives
- CAssess the benefits and impact to the program
- DAmend the risk register with the key project changes
How the community answered
(20 responses)- B5% (1)
- C85% (17)
- D10% (2)
Explanation
When a component project fails to meet its performance objectives, the program manager's first responsibility is to assess the impact on the overall program's benefits delivery. A change request from a project manager signals a potential ripple effect upward. Before deciding to close the project (A), re-baseline the program (B), or update risk registers (D), the program manager must understand how this performance failure affects the program-level benefits and interdependencies. Assessment of benefits and impact provides the information needed to make any subsequent decisions - it is always the logical next step when a component change is introduced.