PGMP · Question #483

PGMP Question #483: Real Exam Question with Answer & Explanation

Sign in or unlock PGMP to reveal the answer and full explanation for question #483. The question stem and answer options stay visible for context.

Benefits Realization Management

Question

A country is in the process of strengthening its defense program. A key project is not meeting its specified performance objectives. The project manager initiates a change request to address this issue. What should the program manager do NEXT?

Options

  • AConsider the option to close out the key project
  • BEvaluate the program and re-baseline the objectives
  • CAssess the benefits and impact to the program
  • DAmend the risk register with the key project changes

Unlock PGMP to see the answer

You've previewed enough free PGMP questions. Unlock PGMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Benefits Realization Management#Program Change Control#Program Governance#Program Performance Monitoring