PK0-004 Practice Questions
1,061 real PK0-004 exam questions with expert-verified answers and explanations. Page 3 of 22.
- Question #101
A project sponsor and Chief Information Officer (CIO) disagree about how to release the final deliverables to the market The sponsor wants to do a massive product release, while th...
- Question #102
The final project report should contain which of the following?
- Question #103
Task B is not planned to start until Task A is completed. Task A is delayed and will not be completed on time. Starting Task B prior to Task A completing is an example of:
- Question #104
The project team is not comfortable moving an expensive material. A third party is hired to move the material. This is an example of risk:
- Question #105
The project's network map has a loop with multiple project outcomes. This is the result of which of the following scheduling tools?
- Question #106
Which of the following tools would a project manager use to determine the root cause of an issue?
- Question #107
Which of the following activity sequencing techniques uses nodes to symbolize activities and arrows to show how their dependencies are connected?
- Question #108
Which of the following activity sequencing techniques uses nodes to symbolize the dependencies of each activity?
- Question #109
The client accepts the critical design review. Which of the following meetings should be held to move to the NEXT step in the project?
- Question #110
A project in the execution phase is over budget, and tasks on the critical path are on schedule. Which of the following should the project manger do NEXT?
- Question #111
A project requires daily status updates. Which of the following is the MOST effective method for providing these updates?
- Question #112
An agreement document that is intended to prevent two or more organizations from sharing specific, confidential information with anyone but each other is called:
- Question #113
A customer will have ongoing changes to project requirements. Which of the following is the BEST project management methodology for this requirement?
- Question #114
A vendor is unable to deliver an order by the specified date. Which of the following should be the project manager's NEXT steps? (Choose two.)
- Question #115
A project manager is working on the project charter. Which of the following phases does this describe?
- Question #116
A company has dictated project scope changes but has stated that the original budget still applies. Which of the following will MOST likely be impacted by the changes?
- Question #117
A project manager was directed to complete a project sooner than previously planned. Which of the following is the MOST cost-effective step to take to ensure the project's success?
- Question #118
A project manager has contracted a third-party vendor to achieve milestones. Which of the following risk strategies is the project manager applying?
- Question #119
A company is hired to perform some of another organization's work. Which of the following types of organizational change is described?
- Question #120
A project has been experiencing some difficulties due to third-party vendors. The project manager should request.
- Question #121
A project's key stakeholders have requested significant changes that will affect the scope. To adjust the project scope, which of the following need to be changed? (Choose two.)
- Question #122
A project has activities on the critical path that must be completed before other activities can start. - Task A is dependent on Task C before Task D can be completed. - Task A req...
- Question #123
During a project, the project manager discovers there is insufficient time allotted for quality control. The project manager prepared to submit a revised schedule to the CCB. Given...
- Question #124
Which of the following job roles is primarily tasked with communicating the project timeline changes?
- Question #125
A project manager is successfully adhering to an eight-week project schedule through week three. A change in the marketplace will require the project manager to deliver the product...
- Question #126
A project manager has been assigned a project with a budget of $50,000. Three change requests are submitted during execution that will increase the overall project cost to $60,000....
- Question #127
The chairperson of the board is visiting from another country and wishes to meet the project team members. The next project team meeting will be held next week, but the chairperson...
- Question #128
Which of the following are characteristics of a project? (Choose two.)
- Question #129
A project team is centralized in a cubicle environment. Periodically, one member disturbs other team members by listening to loud music. Which of the following techniques would be...
- Question #130
A project team has purchased computers with warranties extending throughout the entire project. Which of the following represents the risk strategy utilized?
- Question #131
Which of the following Agile ceremonies is used to determine the backlog items that will be worked on the next weeks?
- Question #132
The project manager of a global project constantly receives complaints from individuals at another location that some team members are not available after lunch on Fridays. This is...
- Question #133
A project manager is providing the lessons learned for a project that ran over budget and produced poor quality deliverables. Which of the following should the project manager incl...
- Question #134
A company decides to give a large section of its development project to another firm to manage and complete because that firm has the appropriately skilled resources to execute the...
- Question #135
An outsourced project team member approaches the project manager and complains that the contract does not permit overtime. The project manager had fast-tracked tasks that require a...
- Question #136
Which of the following roles has approval authority for project funding?
- Question #137
A software upgrade project has been postponed because it may impact a critical business system. Which of the following strategies has been applied?
- Question #138
The project team is distributed throughout a single country. The scrum master has decided to hold remote "stand-ups" on a daily basis. Which of the following would be the MOST effe...
- Question #139
Which of the following is an example of a project?
- Question #140
A project is about to begin the execution phase. The SOW and project plan have been approved, and the project team has been formed. Which of the following types of meetings should...
- Question #141
A department manager asks a project manager about the status of a project that has only a few employees from the department assigned to it. Which of the following were MOST likely...
- Question #142
A part that is needed to complete Task 3 has been backordered and will arrive three days later than scheduled. Task 3 must be complete for Task 4 to start. There is one day of floa...
- Question #143
A software development project is struggling with a certain technology that is unknown to the project team. A project manager has received a third-party proposal to transfer the ri...
- Question #144
A team member learns that an assigned task is not due until the very end of the project. Moreover, the team member is not aware of any predecessor tasks dependent on completing the...
- Question #145
A project manager travels abroad to meet the offshore team and sends out a meeting invitation to review requirements. However, many team members decline the meeting invitation. The...
- Question #146
Which of the following vendor documents specifically address quality? (Select TWO).
- Question #147
A project is coming to the end of a phase. The PMO required that the quality team review the work and budget before moving on to the next phase of the project. The project manager...
- Question #148
Which of the following documents need to be updated as events occur during a project? (Choose two.)
- Question #149
During a project, a key stakeholder asks a project team member to add a requirement. The team member adds the requirement without informing the project manager. Which of the follow...
- Question #150
A project manager is assigned to an ongoing project. Which of the following is the FIRST document the protect manager should review?