PK0-004 · Question #121

A project's key stakeholders have requested significant changes that will affect the scope. To adjust the project scope, which of the following need to be changed? (Choose two.)

The correct answer is B. Project schedule E. WBS. A significant scope change requires updating both the WBS and the project schedule because these two documents directly define and time-bound the work to be performed.

Project management concepts

Question

A project's key stakeholders have requested significant changes that will affect the scope. To adjust the project scope, which of the following need to be changed? (Choose two.)

Options

  • ACost performance parameter
  • BProject schedule
  • CKPI
  • DCorrective action plan
  • EWBS

How the community answered

(39 responses)
  • A
    5% (2)
  • B
    82% (32)
  • C
    3% (1)
  • D
    10% (4)

Why each option

A significant scope change requires updating both the WBS and the project schedule because these two documents directly define and time-bound the work to be performed.

ACost performance parameter

A cost performance parameter (such as CPI) is a monitoring metric used to measure cost efficiency against the baseline; it is not something directly changed to define or authorize a scope adjustment.

BProject scheduleCorrect

The project schedule must be updated because scope changes alter the tasks, durations, and dependencies required to deliver the project, making the existing timeline inaccurate and unreliable.

CKPI

KPIs are performance measurement indicators used to track progress toward objectives; they describe how well the project is performing rather than defining the scope of work to be done.

DCorrective action plan

A corrective action plan is a reactive document used to bring project performance back in line with the baseline; it does not authorize or document a new scope change.

EWBSCorrect

The WBS is the foundational document that decomposes and defines the total scope of the project - any change in scope mandates a corresponding revision to the WBS to accurately reflect the new deliverables and work packages.

Concept tested: Scope change impact on WBS and project schedule

Source: https://www.pmi.org/pmbok-guide-standards/foundational/wbs

Topics

#scope management#WBS#change control#project schedule