CompTIA
PK0-004 · Question #122
PK0-004 Question #122: Real Exam Question with Answer & Explanation
Sign in or unlock PK0-004 to reveal the answer and full explanation for question #122. The question stem and answer options stay visible for context.
Question
A project has activities on the critical path that must be completed before other activities can start. - Task A is dependent on Task C before Task D can be completed. - Task A requires task B to start. - Task B takes twice as long to complete as Task C. Which of the following is the appropriate ordering of the critical path?
Options
- AB, A, D
- BC, B, D, A
- CD, A, C
- DB, C, A, D
Unlock PK0-004 to see the answer
You've previewed enough free PK0-004 questions. Unlock PK0-004 for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.