nerdexam
ExamsPK0-004Questions#123
CompTIA

PK0-004 · Question #123

PK0-004 Question #123: Real Exam Question with Answer & Explanation

The correct answer is B: 16 days. You need to add a day for Tasks 1, 3 ,4 and 5 (critical path items) and the total days (not including the weekends) is 16.

Question

During a project, the project manager discovers there is insufficient time allotted for quality control. The project manager prepared to submit a revised schedule to the CCB. Given the attached chart, which of the following is the critical path if one day is added to each task for quality control?

Exhibit

PK0-004 question #123 exhibit

Options

  • A12 days
  • B16 days
  • C17 days
  • D22 days

Explanation

You need to add a day for Tasks 1, 3 ,4 and 5 (critical path items) and the total days (not including the weekends) is 16.

Community Discussion

No community discussion yet for this question.

Full PK0-004 Practice