CompTIA
PK0-004 · Question #123
During a project, the project manager discovers there is insufficient time allotted for quality control. The project manager prepared to submit a revised schedule to the CCB. Given the attached…
The correct answer is B. 16 days. You need to add a day for Tasks 1, 3 ,4 and 5 (critical path items) and the total days (not including the weekends) is 16.
Tools and documentation
Question
During a project, the project manager discovers there is insufficient time allotted for quality control. The project manager prepared to submit a revised schedule to the CCB. Given the attached chart, which of the following is the critical path if one day is added to each task for quality control?
Exhibits
Options
- A12 days
- B16 days
- C17 days
- D22 days
How the community answered
(30 responses)- A30% (9)
- B47% (14)
- C7% (2)
- D17% (5)
Explanation
You need to add a day for Tasks 1, 3 ,4 and 5 (critical path items) and the total days (not including the weekends) is 16.
Topics
#critical path analysis#schedule adjustment#quality control#Gantt chart
Community Discussion
No community discussion yet for this question.


