PK0-004 · Question #124

Which of the following job roles is primarily tasked with communicating the project timeline changes?

The correct answer is A. Project scheduler. The project scheduler is responsible for developing and maintaining the project schedule, communicating the timelines and due dates, reporting schedule performance, and communicating any schedule changes to the stakeholders and project team members.

Project management concepts

Question

Which of the following job roles is primarily tasked with communicating the project timeline changes?

Options

  • AProject scheduler
  • BProject manager
  • CProject sponsor
  • DProject coordinator

How the community answered

(32 responses)
  • A
    91% (29)
  • B
    3% (1)
  • C
    6% (2)

Explanation

The project scheduler is responsible for developing and maintaining the project schedule, communicating the timelines and due dates, reporting schedule performance, and communicating any schedule changes to the stakeholders and project team members.

Topics

#project roles#project scheduler#timeline communication#responsibility