nerdexam
CompTIA

PK0-004 · Question #125

A project manager is successfully adhering to an eight-week project schedule through week three. A change in the marketplace will require the project manager to deliver the product one week early…

The correct answer is B. Predecessors G. Float. If accelerated schedule means fast tracking, if task 1 and task 4 can run at the same time, you've already saved a week, but nothing in the chart currently tells us that, if they're all Finish to Start, then that won't help. With float time, we can determine if we can eliminate…

Tools and documentation

Question

A project manager is successfully adhering to an eight-week project schedule through week three. A change in the marketplace will require the project manager to deliver the product one week early. Given the project schedule above, which of the following aspects are missing for the project manager to plan and execute an accelerated schedule? (Choose two).

Exhibits

PK0-004 question #125 exhibit 1
PK0-004 question #125 exhibit 2
PK0-004 question #125 exhibit 3

Options

  • ACost
  • BPredecessors
  • CLag
  • DDurations
  • EResource loading
  • FSubtasks
  • GFloat

How the community answered

(18 responses)
  • B
    67% (12)
  • C
    6% (1)
  • D
    11% (2)
  • F
    17% (3)

Explanation

If accelerated schedule means fast tracking, if task 1 and task 4 can run at the same time, you've already saved a week, but nothing in the chart currently tells us that, if they're all Finish to Start, then that won't help. With float time, we can determine if we can eliminate enough of a lead float time to shave a week off the schedule.

Topics

#schedule compression#predecessors#float#critical path

Community Discussion

No community discussion yet for this question.

Full PK0-004 Practice