CompTIA
PK0-004 · Question #120
PK0-004 Question #120: Real Exam Question with Answer & Explanation
The correct answer is C: A risk register update. When a project experiences difficulties caused by third-party vendors, the project manager should update the risk register to formally document and track those vendor-related risks.
Question
A project has been experiencing some difficulties due to third-party vendors. The project manager should request.
Options
- AAdditional resources
- BA gate review
- CA risk register update
- DA performance audit
Explanation
When a project experiences difficulties caused by third-party vendors, the project manager should update the risk register to formally document and track those vendor-related risks.
Common mistakes.
- A. Requesting additional resources addresses capacity or staffing shortfalls, not the documentation and management of risks introduced by external vendor problems.
- B. A gate review is a formal phase-end checkpoint used to authorize moving to the next project phase, not a mechanism for managing ongoing vendor-related risks mid-project.
- D. A performance audit evaluates whether a vendor or process is meeting defined standards, but it does not serve as the primary tool for identifying, documenting, and tracking risks in the risk management process.
Concept tested. Risk register update for vendor-related project risks
Reference. https://www.pmi.org/pmbok-guide-standards/foundational/pmbok
Community Discussion
No community discussion yet for this question.