PK0-004 · Question #131

PK0-004 Question #131: Real Exam Question with Answer & Explanation

The correct answer is B: Sprint planning meeting. Sprint planning is the Scrum ceremony specifically designed to select and commit to product backlog items that the team will work on during the upcoming sprint.

Question

Which of the following Agile ceremonies is used to determine the backlog items that will be worked on the next weeks?

Exhibit

PK0-004 question #131 exhibit

Options

  • ASCRUM retrospective meeting
  • BSprint planning meeting
  • CDaily standup meeting
  • DReview meeting

Explanation

Sprint planning is the Scrum ceremony specifically designed to select and commit to product backlog items that the team will work on during the upcoming sprint.

Common mistakes.

  • A. The retrospective meeting focuses on inspecting and improving the team's process and practices from the previous sprint, not on selecting future backlog items.
  • C. The daily standup (daily scrum) is a short synchronization meeting to review progress toward the sprint goal and identify blockers - not for backlog selection.
  • D. The review meeting (sprint review) is held at the end of the sprint to demonstrate completed work to stakeholders, not to plan what will be worked on next.

Concept tested. Agile Scrum sprint planning ceremony purpose

Reference. https://scrumguides.org/scrum-guide.html#sprint-planning