PK0-004 · Question #131

Which of the following Agile ceremonies is used to determine the backlog items that will be worked on the next weeks?

The correct answer is B. Sprint planning meeting. Sprint planning is the Scrum ceremony specifically designed to select and commit to product backlog items that the team will work on during the upcoming sprint.

Project management concepts

Question

Which of the following Agile ceremonies is used to determine the backlog items that will be worked on the next weeks?

Exhibit

PK0-004 question #131 exhibit

Options

  • ASCRUM retrospective meeting
  • BSprint planning meeting
  • CDaily standup meeting
  • DReview meeting

How the community answered

(32 responses)
  • A
    3% (1)
  • B
    91% (29)
  • D
    6% (2)

Why each option

Sprint planning is the Scrum ceremony specifically designed to select and commit to product backlog items that the team will work on during the upcoming sprint.

ASCRUM retrospective meeting

The retrospective meeting focuses on inspecting and improving the team's process and practices from the previous sprint, not on selecting future backlog items.

BSprint planning meetingCorrect

The sprint planning meeting is held at the start of each sprint and involves the development team and product owner selecting items from the product backlog to pull into the sprint backlog. The team defines the sprint goal and determines how much work can be completed in the upcoming iteration, directly answering what will be worked on next.

CDaily standup meeting

The daily standup (daily scrum) is a short synchronization meeting to review progress toward the sprint goal and identify blockers - not for backlog selection.

DReview meeting

The review meeting (sprint review) is held at the end of the sprint to demonstrate completed work to stakeholders, not to plan what will be worked on next.

Concept tested: Agile Scrum sprint planning ceremony purpose

Source: https://scrumguides.org/scrum-guide.html#sprint-planning