PK0-004 · Question #132

The project manager of a global project constantly receives complaints from individuals at another location that some team members are not available after lunch on Fridays. This is acceptable to the…

The correct answer is D. Time zone. Team members at a remote location being unavailable after lunch on Fridays in a global project is most likely caused by time zone differences making that period fall outside their local working hours.

Project management concepts

Question

The project manager of a global project constantly receives complaints from individuals at another location that some team members are not available after lunch on Fridays. This is acceptable to the project manager. Which of the following factors is the MOST likely cause for this scenario?

Options

  • APersonal preference
  • BIntra-organizational differences
  • CCulture
  • DTime zone

How the community answered

(52 responses)
  • A
    2% (1)
  • B
    6% (3)
  • C
    2% (1)
  • D
    90% (47)

Why each option

Team members at a remote location being unavailable after lunch on Fridays in a global project is most likely caused by time zone differences making that period fall outside their local working hours.

APersonal preference

Personal preference would not explain a consistent, location-wide pattern of unavailability tied to a specific day and time across multiple team members.

BIntra-organizational differences

Intra-organizational differences refer to varying internal policies or structural differences within the company, not a time-based geographic availability pattern.

CCulture

While cultural observances like Friday afternoon prayers could cause this in some regions, time zone differences are a more universally applicable and likely explanation for recurring availability gaps in global teams.

DTime zoneCorrect

In globally distributed projects, time zone offsets mean that 'after lunch' at the project manager's location can correspond to evening or end-of-day hours at a remote location - for example, a team 8+ hours ahead would already be past their workday. This is a recognized and acceptable scheduling constraint in global project management, which is why the project manager finds the situation acceptable.

Concept tested: Time zone impact on global project team availability

Topics

#virtual teams#time zones#global project#distributed teams