A project manager is providing the lessons learned for a project that ran over budget and produced poor quality deliverables. Which of the following should the project manager include as part of the…
The correct answer is B. Post-mortem analysis. https://en.wikipedia.org/wiki/Postmortem_documentation
Project life cycle phases
Question
A project manager is providing the lessons learned for a project that ran over budget and produced poor quality deliverables. Which of the following should the project manager include as part of the lessons learned?
Exhibit
Options
- ARisk register
- BPost-mortem analysis
- CIssue log
- DProcurement report
How the community answered
(35 responses)- A3% (1)
- B91% (32)
- D6% (2)
Explanation
Topics
#lessons learned#post-mortem analysis#project closure#knowledge management