A project manager is providing the lessons learned for a project that ran over budget and produced poor quality deliverables. Which of the following should the project manager include as part of the…

The correct answer is B. Post-mortem analysis. https://en.wikipedia.org/wiki/Postmortem_documentation

Project life cycle phases

Question

A project manager is providing the lessons learned for a project that ran over budget and produced poor quality deliverables. Which of the following should the project manager include as part of the lessons learned?

Exhibit

PK0-004 question #133 exhibit

Options

  • ARisk register
  • BPost-mortem analysis
  • CIssue log
  • DProcurement report

How the community answered

(35 responses)
  • A
    3% (1)
  • B
    91% (32)
  • D
    6% (2)

Explanation

https://en.wikipedia.org/wiki/Postmortem_documentation

Topics

#lessons learned#post-mortem analysis#project closure#knowledge management

Community Discussion

No community discussion yet for this question.

Full PK0-004 Practice