PK0-004 · Question #103

Task B is not planned to start until Task A is completed. Task A is delayed and will not be completed on time. Starting Task B prior to Task A completing is an example of:

The correct answer is B. Fast tracking. Rolling-wave planning is the process of project planning in waves as the project proceeds and later details become clearer. Crashing is dedicating extra resources to meet a short deadline.

Project management concepts

Question

Task B is not planned to start until Task A is completed. Task A is delayed and will not be completed on time. Starting Task B prior to Task A completing is an example of:

Options

  • AManaging change
  • BFast tracking
  • CRolling wave planning
  • DCrashing

How the community answered

(27 responses)
  • A
    4% (1)
  • B
    85% (23)
  • C
    4% (1)
  • D
    7% (2)

Explanation

Rolling-wave planning is the process of project planning in waves as the project proceeds and later details become clearer. Crashing is dedicating extra resources to meet a short deadline.

Topics

#fast tracking#schedule compression#task dependencies#critical path