PK0-004 · Question #103
Task B is not planned to start until Task A is completed. Task A is delayed and will not be completed on time. Starting Task B prior to Task A completing is an example of:
The correct answer is B. Fast tracking. Rolling-wave planning is the process of project planning in waves as the project proceeds and later details become clearer. Crashing is dedicating extra resources to meet a short deadline.
Project management concepts
Question
Task B is not planned to start until Task A is completed. Task A is delayed and will not be completed on time. Starting Task B prior to Task A completing is an example of:
Options
- AManaging change
- BFast tracking
- CRolling wave planning
- DCrashing
How the community answered
(27 responses)- A4% (1)
- B85% (23)
- C4% (1)
- D7% (2)
Explanation
Rolling-wave planning is the process of project planning in waves as the project proceeds and later details become clearer. Crashing is dedicating extra resources to meet a short deadline.
Topics
#fast tracking#schedule compression#task dependencies#critical path