PK0-004 · Question #102
The final project report should contain which of the following?
The correct answer is D. Summary of the project cost. The final project report is a high-level closing document that summarizes outcomes, and a summary of project cost is standard content for that report.
Question
The final project report should contain which of the following?
Options
- AMinutes of all the project meetings
- BProject design documentation
- CDetailed breakdown of the schedule
- DSummary of the project cost
How the community answered
(22 responses)- A5% (1)
- C5% (1)
- D91% (20)
Why each option
The final project report is a high-level closing document that summarizes outcomes, and a summary of project cost is standard content for that report.
Meeting minutes are operational records created throughout the project lifecycle and are not compiled into the final project report.
Design documentation is a technical artifact belonging to the project deliverables or technical records, not a component of the final project report.
A detailed schedule breakdown is an operational project management artifact used during execution, not a summary-level item appropriate for the final report.
The final project report is a closure artifact that provides a summary-level review of how the project performed against its baselines, including cost performance. A cost summary communicates to stakeholders and sponsors whether the project was delivered within budget and documents final financial outcomes. This information is essential for organizational learning and future project planning.
Concept tested: Project closure - final report contents
Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok