Question

A project sponsor and Chief Information Officer (CIO) disagree about how to release the final deliverables to the market The sponsor wants to do a massive product release, while the CIO wants to be extremely cautious and add more time for testing and defect resolution. The project manager works with both parties and determines the best solution is to roll the product out in a pilot release to see how it tests, and then use customer feedback to determine next steps. Which of the following conflict resolution techniques is the project manager using?

Options

  • AForcing
  • BNegotiating
  • CCompromising
  • DAvoiding

Unlock PK0-004 to see the answer

You've previewed enough free PK0-004 questions. Unlock PK0-004 for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Full PK0-004 Practice