A project manager is attempting to establish the proper sequencing and duration of project activities. Which of the following would be the MOST beneficial?
The correct answer is A. Network diagram. Network Diagram: used to illustrate the sequence and dependencies for activities in a project.
Tools and documentation
Question
A project manager is attempting to establish the proper sequencing and duration of project activities. Which of the following would be the MOST beneficial?
Options
- ANetwork diagram
- BIshikawa diagram
- CWBS
- DGantt chart
How the community answered
(55 responses)- A91% (50)
- B5% (3)
- C2% (1)
- D2% (1)
Explanation
Network Diagram: used to illustrate the sequence and dependencies for activities in a project.
Topics
#network diagram#activity sequencing#schedule management#activity duration