PK0-004 · Question #99
A critical stakeholder has requested additional status updated beyond the schedule. Which of the following factors MOST likely needs to be accounted for when communication with this stakeholder?
The correct answer is C. Frequency. Stakeholder wants ADDITIONAL status updates rather than the normal scheduled one. Therefore they need to keep "frequent" updates in mind because he wants more than just scheduled ones.
Project management concepts
Question
A critical stakeholder has requested additional status updated beyond the schedule. Which of the following factors MOST likely needs to be accounted for when communication with this stakeholder?
Options
- AConfidentiality
- BCriticality
- CFrequency
- DCultural differences
How the community answered
(39 responses)- A3% (1)
- B5% (2)
- C92% (36)
Explanation
Stakeholder wants ADDITIONAL status updates rather than the normal scheduled one. Therefore they need to keep "frequent" updates in mind because he wants more than just scheduled ones.