PK0-004 · Question #99

A critical stakeholder has requested additional status updated beyond the schedule. Which of the following factors MOST likely needs to be accounted for when communication with this stakeholder?

The correct answer is C. Frequency. Stakeholder wants ADDITIONAL status updates rather than the normal scheduled one. Therefore they need to keep "frequent" updates in mind because he wants more than just scheduled ones.

Project management concepts

Question

A critical stakeholder has requested additional status updated beyond the schedule. Which of the following factors MOST likely needs to be accounted for when communication with this stakeholder?

Options

  • AConfidentiality
  • BCriticality
  • CFrequency
  • DCultural differences

How the community answered

(39 responses)
  • A
    3% (1)
  • B
    5% (2)
  • C
    92% (36)

Explanation

Stakeholder wants ADDITIONAL status updates rather than the normal scheduled one. Therefore they need to keep "frequent" updates in mind because he wants more than just scheduled ones.

Topics

#communication frequency#stakeholder management#status reporting#communication planning