A project is coming to the end of a phase. The PMO required that the quality team review the work and budget before moving on to the next phase of the project. The project manager must schedule the…

The correct answer is B. a milestone. A scheduled phase-end review where stakeholders and the PMO assess work and budget before advancing is defined as a milestone - a significant, planned checkpoint in the project timeline.

Project life cycle phases

Question

A project is coming to the end of a phase. The PMO required that the quality team review the work and budget before moving on to the next phase of the project. The project manager must schedule the review of the phase and have the stakeholders present. This review is referred to as:

Options

  • Achange management.
  • Ba milestone.
  • Ca tollgate.
  • Dan incident response.

How the community answered

(21 responses)
  • A
    5% (1)
  • B
    90% (19)
  • C
    5% (1)

Why each option

A scheduled phase-end review where stakeholders and the PMO assess work and budget before advancing is defined as a milestone - a significant, planned checkpoint in the project timeline.

Achange management.

Change management is the structured process for requesting, evaluating, and approving modifications to project scope, schedule, or cost baselines, not a scheduled phase-end review.

Ba milestone.Correct

A milestone is a significant, zero-duration point in the project schedule that marks the completion of a major deliverable or phase. Phase-end reviews mandated by the PMO, where quality and budget are formally assessed before the project advances, are designated as milestones because they represent a measurable, planned checkpoint. This type of scheduled review with stakeholder sign-off confirms phase completion and is built into the project timeline as a formal control point.

Ca tollgate.

A tollgate is a narrower go/no-go decision point specifically focused on authorization to proceed, whereas a milestone is the broader scheduled event that encompasses the full phase-end review described in the scenario.

Dan incident response.

Incident response is a reactive process for addressing unplanned failures or security events, not a planned, scheduled review with PMO and stakeholders.

Concept tested: Project milestone and phase-end review definition

Source: https://www.pmi.org/pmbok-guide-standards/lexicon

Topics

#phase review#milestone#tollgate#project governance