PK0-004 · Question #107

Which of the following activity sequencing techniques uses nodes to symbolize activities and arrows to show how their dependencies are connected?

The correct answer is D. Precedence Diagramming Method. The precedence diagram method (PDM) is a tool for scheduling activities in a project plan. It is a method of constructing a project schedule network diagram that uses boxes, referred to as nodes, to represent activities and connects them with arrows that show the dependencies

Tools and documentation

Question

Which of the following activity sequencing techniques uses nodes to symbolize activities and arrows to show how their dependencies are connected?

Options

  • ACritical Path Method
  • BArrow Diagramming Method
  • CCritical Chain Method
  • DPrecedence Diagramming Method

How the community answered

(42 responses)
  • A
    5% (2)
  • B
    2% (1)
  • C
    2% (1)
  • D
    90% (38)

Explanation

The precedence diagram method (PDM) is a tool for scheduling activities in a project plan. It is a method of constructing a project schedule network diagram that uses boxes, referred to as nodes, to represent activities and connects them with arrows that show the dependencies

Topics

#Precedence Diagramming Method#activity sequencing#network diagram#dependencies