PK0-004 · Question #108
Which of the following activity sequencing techniques uses nodes to symbolize the dependencies of each activity?
The correct answer is C. Arrow Diagramming Method. An arrow diagram is defined as a process diagramming tool used to determine optimal sequence of events, and their interconnectivity. It is used for scheduling and to determine the critical path through nodes. The arrow diagramming method shows the required order of tasks in a…
Question
Which of the following activity sequencing techniques uses nodes to symbolize the dependencies of each activity?
Options
- ACritical Path Method
- BCritical Chain Method
- CArrow Diagramming Method
- DGantt Chart Method
How the community answered
(19 responses)- B5% (1)
- C89% (17)
- D5% (1)
Explanation
An arrow diagram is defined as a process diagramming tool used to determine optimal sequence of events, and their interconnectivity. It is used for scheduling and to determine the critical path through nodes. The arrow diagramming method shows the required order of tasks in a project or process, the best schedule for the entire project, and potential scheduling and resource problems and their solutions. The arrow diagram lets you calculate the "critical path" of the project.
Topics