PK0-004 · Question #109
The client accepts the critical design review. Which of the following meetings should be held to move to the NEXT step in the project?
The correct answer is B. Kickoff. After a formal gate review such as a critical design review is accepted, a kickoff meeting is held to officially launch and align the team on the next phase of the project.
Question
The client accepts the critical design review. Which of the following meetings should be held to move to the NEXT step in the project?
Options
- AExecution
- BKickoff
- CClosure
- DPlanning
How the community answered
(29 responses)- A10% (3)
- B69% (20)
- C3% (1)
- D17% (5)
Why each option
After a formal gate review such as a critical design review is accepted, a kickoff meeting is held to officially launch and align the team on the next phase of the project.
Execution is a project phase or process group, not a type of meeting - calling an 'execution meeting' is not a standard project management practice used to transition between phases.
A kickoff meeting serves as the formal starting point for a project phase, bringing together the team and stakeholders to align on objectives, roles, and the work ahead. After the client accepts the critical design review - a gate that closes the design phase - a kickoff meeting is the appropriate next step to transition the team into the implementation or build phase and ensure everyone is aligned before work begins.
A closure meeting is conducted at the end of a project or phase to document lessons learned, obtain formal acceptance, and release resources - it is not used to move forward into new work.
Planning meetings occur earlier in the project lifecycle to develop the project management plan - by the time a critical design review has been accepted, the planning for that phase is already complete.
Concept tested: Kickoff meeting as phase transition milestone
Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok