The correct answer is A: Initiation. The project charter formally authorizes a project and is the primary deliverable of the Initiation phase of the project lifecycle.

Question

A project manager is working on the project charter. Which of the following phases does this describe?

Options

  • AInitiation
  • BPlanning
  • CExecution
  • DClosing

Explanation

The project charter formally authorizes a project and is the primary deliverable of the Initiation phase of the project lifecycle.

Common mistakes.

  • B. Planning involves developing the project management plan and its subsidiary plans after the charter has already been approved and the project formally initiated.
  • C. Execution is where the actual project deliverables are produced according to the approved plan; the charter must already exist and be authorized before this phase begins.
  • D. Closing involves finalizing all project activities, obtaining stakeholder acceptance, and archiving records - the charter is a foundational input document, not a closing artifact.

Concept tested. Project charter as the Initiation phase deliverable

Reference. https://www.pmi.org/pmbok-guide-standards