The correct answer is A: Initiation. The project charter formally authorizes a project and is the primary deliverable of the Initiation phase of the project lifecycle.
Question
A project manager is working on the project charter. Which of the following phases does this describe?
Options
- AInitiation
- BPlanning
- CExecution
- DClosing
Explanation
The project charter formally authorizes a project and is the primary deliverable of the Initiation phase of the project lifecycle.
Common mistakes.
- B. Planning involves developing the project management plan and its subsidiary plans after the charter has already been approved and the project formally initiated.
- C. Execution is where the actual project deliverables are produced according to the approved plan; the charter must already exist and be authorized before this phase begins.
- D. Closing involves finalizing all project activities, obtaining stakeholder acceptance, and archiving records - the charter is a foundational input document, not a closing artifact.
Concept tested. Project charter as the Initiation phase deliverable
Reference. https://www.pmi.org/pmbok-guide-standards