nerdexam
CompTIA

PK0-004 · Question #116

A company has dictated project scope changes but has stated that the original budget still applies. Which of the following will MOST likely be impacted by the changes?

The correct answer is C. Schedule. When project scope increases but the budget is held constant, the triple constraint means the schedule absorbs the impact because additional resources cannot be funded.

Project management concepts

Question

A company has dictated project scope changes but has stated that the original budget still applies. Which of the following will MOST likely be impacted by the changes?

Options

  • AQuality
  • BRegulations
  • CSchedule
  • Dproject team

How the community answered

(66 responses)
  • A
    11% (7)
  • B
    6% (4)
  • C
    80% (53)
  • D
    3% (2)

Why each option

When project scope increases but the budget is held constant, the triple constraint means the schedule absorbs the impact because additional resources cannot be funded.

AQuality

Quality may eventually degrade if the team is overextended, but the most immediate and measurable impact of increased scope with a fixed budget is on the project timeline, not quality.

BRegulations

Regulations are external legal or compliance requirements imposed by governing bodies and are not determined by internal project scope or budget decisions.

CScheduleCorrect

The triple constraint (scope, cost, time) dictates that changes to one constraint affect the others; with scope expanded and cost fixed, no additional staff or resources can be procured, forcing the existing team to do more work within the same window and directly extending the schedule.

Dproject team

The project team's composition is not a direct output of a scope-budget conflict; the team is expected to absorb the additional work, which impacts the schedule before any team restructuring would occur.

Concept tested: Triple constraint trade-offs - scope, cost, and schedule

Source: https://www.pmi.org/pmbok-guide-standards

Topics

#triple constraint#scope change#budget constraint#schedule impact

Community Discussion

No community discussion yet for this question.

Full PK0-004 Practice