A part that is needed to complete Task 3 has been backordered and will arrive three days later than scheduled. Task 3 must be complete for Task 4 to start. There is one day of float for the two…

The correct answer is C. Two. The question states that the part will arrive 3 days late. If there was zero float, then yes it would be delayed 3 days. However there is 1 day of float time so 3-1=2. The answer should be C - 2

Project management concepts

Question

A part that is needed to complete Task 3 has been backordered and will arrive three days later than scheduled. Task 3 must be complete for Task 4 to start. There is one day of float for the two tasks. Which of the following represents the number of days the project schedule will be delayed?

Options

  • AZero
  • BOne
  • CTwo
  • DThree

How the community answered

(35 responses)
  • A
    6% (2)
  • B
    11% (4)
  • C
    80% (28)
  • D
    3% (1)

Explanation

The question states that the part will arrive 3 days late. If there was zero float, then yes it would be delayed 3 days. However there is 1 day of float time so 3-1=2. The answer should be C - 2

Topics

#float#critical path#schedule delay#task dependencies