PK0-004 · Question #142
A part that is needed to complete Task 3 has been backordered and will arrive three days later than scheduled. Task 3 must be complete for Task 4 to start. There is one day of float for the two…
The correct answer is C. Two. The question states that the part will arrive 3 days late. If there was zero float, then yes it would be delayed 3 days. However there is 1 day of float time so 3-1=2. The answer should be C - 2
Question
A part that is needed to complete Task 3 has been backordered and will arrive three days later than scheduled. Task 3 must be complete for Task 4 to start. There is one day of float for the two tasks. Which of the following represents the number of days the project schedule will be delayed?
Options
- AZero
- BOne
- CTwo
- DThree
How the community answered
(35 responses)- A6% (2)
- B11% (4)
- C80% (28)
- D3% (1)
Explanation
The question states that the part will arrive 3 days late. If there was zero float, then yes it would be delayed 3 days. However there is 1 day of float time so 3-1=2. The answer should be C - 2