nerdexam
CompTIA

PK0-004 · Question #141

A department manager asks a project manager about the status of a project that has only a few employees from the department assigned to it. Which of the following were MOST likely missed during…

The correct answer is B. Resource analysis and Gantt chart. A Gantt chart would give the schedule for how long the resources from the department are needed and the resource analysis will show contrast to using the employees for the project and not using them in the department.

Tools and documentation

Question

A department manager asks a project manager about the status of a project that has only a few employees from the department assigned to it. Which of the following were MOST likely missed during project planning?

Options

  • AIssue log and process diagram
  • BResource analysis and Gantt chart
  • CStakeholder analysis and communication plan
  • DScatter chart and scope analysis

How the community answered

(33 responses)
  • A
    3% (1)
  • B
    85% (28)
  • C
    9% (3)
  • D
    3% (1)

Explanation

A Gantt chart would give the schedule for how long the resources from the department are needed and the resource analysis will show contrast to using the employees for the project and not using them in the department.

Topics

#resource analysis#Gantt chart#project planning#stakeholder communication

Community Discussion

No community discussion yet for this question.

Full PK0-004 Practice