PK0-004 · Question #140

A project is about to begin the execution phase. The SOW and project plan have been approved, and the project team has been formed. Which of the following types of meetings should happen NEXT?

The correct answer is C. Kickoff. There are a variety of versions of when the appropriate time for a Kick-off meeting is. CompTIA and PMI would typically recommend that you hold the Kick-off meeting after all planning is completed and before you begin to execute work. Others may have Kick-off meetings before…

Project life cycle phases

Question

A project is about to begin the execution phase. The SOW and project plan have been approved, and the project team has been formed. Which of the following types of meetings should happen NEXT?

Options

  • AUpdate
  • BScheduling
  • CKickoff
  • DReview

How the community answered

(53 responses)
  • A
    2% (1)
  • B
    4% (2)
  • C
    89% (47)
  • D
    6% (3)

Explanation

There are a variety of versions of when the appropriate time for a Kick-off meeting is. CompTIA and PMI would typically recommend that you hold the Kick-off meeting after all planning is completed and before you begin to execute work. Others may have Kick-off meetings before any planning is done and directly after the project charter has given you authorization to begin project

Topics

#kickoff meeting#execution phase#project lifecycle#project initiation