An outsourced project team member approaches the project manager and complains that the contract does not permit overtime. The project manager had fast-tracked tasks that require additional hours…

The correct answer is B. MOA. Memorandum of Agreement (MOA) is a “conditional agreement” between two or more parties where the transfer of funds for services are anticipated. The MOA is prepared in advance of a support agreement/reimbursable order form that defines the support, basis for reimbursement, the…

Tools and documentation

Question

An outsourced project team member approaches the project manager and complains that the contract does not permit overtime. The project manager had fast-tracked tasks that require additional hours. Which of the following documents did the project manager fail to reference?

Options

  • AMOU
  • BMOA
  • CSOW
  • DSLA

How the community answered

(30 responses)
  • A
    3% (1)
  • B
    73% (22)
  • C
    17% (5)
  • D
    7% (2)

Explanation

Memorandum of Agreement (MOA) is a “conditional agreement” between two or more parties where the transfer of funds for services are anticipated. The MOA is prepared in advance of a support agreement/reimbursable order form that defines the support, basis for reimbursement, the billing and payment process, and other terms and conditions of the agreement. MOAs often establish common legal terms that will be read into every reimbursable order that follows. MOAs do not obligate any funds themselves, but they establish the terms for future service and cite one of the appropriate authorities to do so.

Topics

#MOA#contract documents#procurement#overtime policy