nerdexam
CompTIA

PK0-004 · Question #137

A software upgrade project has been postponed because it may impact a critical business system. Which of the following strategies has been applied?

The correct answer is C. Avoid risk. Postponing a software upgrade to prevent impact to a critical business system is a risk avoidance strategy, which eliminates a threat by changing or deferring the planned action.

Project management concepts

Question

A software upgrade project has been postponed because it may impact a critical business system. Which of the following strategies has been applied?

Options

  • AAccept risk
  • BMitigate risk
  • CAvoid risk
  • DExploit risk

How the community answered

(25 responses)
  • A
    8% (2)
  • C
    88% (22)
  • D
    4% (1)

Why each option

Postponing a software upgrade to prevent impact to a critical business system is a risk avoidance strategy, which eliminates a threat by changing or deferring the planned action.

AAccept risk

Accepting risk means acknowledging the threat and proceeding with the original plan without changing scope or schedule, which is the opposite of postponing the project.

BMitigate risk

Mitigating risk reduces the probability or impact of a risk while still proceeding with the work, whereas postponing the project eliminates the risk entirely rather than lessening it.

CAvoid riskCorrect

Risk avoidance involves modifying the project plan - in this case postponing the upgrade - to completely eliminate the threat rather than reduce or accept it. By deferring the work, the organization removes the scenario in which the critical system could be impacted, which is the defining characteristic of avoidance as opposed to other risk response strategies.

DExploit risk

Exploiting risk is a response strategy for positive risks (opportunities) aimed at ensuring the benefit is realized, and does not apply to threats such as potential system impact.

Concept tested: Risk avoidance strategy in project risk management

Topics

#risk avoidance#risk strategies#risk response#software project