- Question #751Project management concepts
A project manager launched a survey for future end users of a new product under development. The sponsor received the survey results and realized the needs are different than the f...
project cancellationcost constraintsscope changessponsor decisions - Question #752Project management concepts
The responsibility of estimating how long a task will take belongs to the:
task estimationproject teamroles and responsibilitiesduration estimating - Question #753Tools and documentation
A project manager is managing an eight-month effort and has to report on the financial health once a month. No changes to the project will be approved going forward. Given the foll...
burn ratefinancial healthcost forecastingearned value - Question #754Project management concepts
A company is reviewing its strategic goals for several unrelated efforts. The company is considering the efforts as:
portfolio managementstrategic goalsprogram vs portfolioorganizational planning - Question #755Project management concepts
A project manager realizes there is a significant risk event. Which of the following is the FIRST step the project manager should perform?
risk managementcontingency planrisk responserisk events - Question #756Project life cycle phases
A newly developed claims processing system will require users of the prior system to be trained to use the new system. During which of the following project phases should the train...
closing phaseuser trainingsystem transitionproject phases - Question #757Project management concepts
The Chief Executive Officer (CEO) informs the project manager that a project must be completed six months earlier than previously scheduled. Which of the following is the BEST way...
schedule compressionscope reductiontriple constraintchange management - Question #758Tools and documentation
Which of the following documents would MOST likely provide a broad, non-customized overview of a product or service?
SLAprocurement documentsRFIvendor communication - Question #759Tools and documentation
During a project, the purpose of examining the cost baseline is to:
cost baselinebudget planningfinancial forecastingproject budget - Question #760Project management concepts
A construction company has not been on the job for more than two weeks. Which of the following is an example of how a project manager can utilize the transfer risk strategy?
risk transferrisk response strategiesprocurementvendor management - Question #761Project management concepts
Which of the following documents will MOST likely result in a time and material agreement?
procurement documentsSLAtime and material contractcontract types - Question #762Tools and documentation
A project requires the distribution of training materials for 300 stakeholders across multiple campuses. Which of the following would be the BEST method to deliver the materials?
communication methodsstakeholder distributiontraining materialsemail - Question #763Project management concepts
A project requires that laptops be obtained immediately. The project manager confirms existing laptops, which were used for a previous project, are available, but authorization is...
risk response strategiesexploitpositive riskresource reuse - Question #764Project management concepts
Which of the following organizational changes is MOST likely used to transfer staff resources from one city to another to support team activities?
organizational changeresource managementrelocationstaffing - Question #765Tools and documentation
Which of the following indicators will assist the project manager in determining the health of the budget?
earned value managementCPIbudget healthperformance indicators - Question #766Project life cycle phases
A project is due to deliver, configure, and install a collection of medical devices. The first device in the collection is reportedly four weeks behind schedule is manufacturing. W...
schedule managementdelay responseinstallation reorderingvendor delay - Question #767Tools and documentation
A project manager is sending regular status reports; however, many team members seem to be unaware of the overall project status. Which of the following should the project manager...
communication managementstatus reportsdistribution listteam awareness - Question #768Project management concepts
Given the status report excerpt below: Overall status: The project is tracking well. Tasks are being completed on time. Costs are lower than expected. Risk/issues are regularly bei...
status reportingrisk monitoringrisk triggersrisk analysis - Question #769Project management concepts
A project manager decides to release a product one month later, knowing marketing studies have shown doing so could require increased manufacturing capacity. Which of the following...
risk response strategiesacceptschedule riskopportunity management - Question #770Project life cycle phases
The problem statement of a project helps to identify:
problem statementproject initiationproject purposescope definition - Question #771Project management concepts
Joe, a project team member, was hired after a project was already underway, and he is the only team member who does not have an office. Ann, the project manager, is aware of Joe's...
conflict resolutionsmoothingteam dynamicsproject environment - Question #772Tools and documentation
A project manager is developing a network diagram to understand the flow of a project. Which of the following processes is the project manager performing?
network diagramsequencing activitiesschedule planningactivity dependencies - Question #773Project life cycle phases
Which of the following should receive regular communication during the planning phase of a project? (Choose two.)
planning phasestakeholder communicationsponsor engagementSMEs - Question #774Tools and documentation
A project sponsor is not being updated on the project as expected. Instead of receiving information on a monthly basis, the project sponsor wants to see it biweekly and requests th...
communication planstakeholder managementcommunication frequencyplan updates - Question #775Tools and documentation
Detailed policy guidance is BEST provided by:
policy guidancecommunication channelsintranetinformation distribution - Question #776Project management concepts
A project manager has just received an extra resource from a functional manager. Which of the following activities is the BEST to consider for assignment to the resource?
resource managementactivity assignmentskillset matchingresource allocation - Question #777Tools and documentation
A project needs to know if a project is progressing as planned. Which of the following tools would be BEST to measure progress?
critical path methodproject monitoringprogress measurementschedule tools - Question #778Basics of IT and governance
A security breach was identified within a large company. The authentication server crashed, and employees are unable to access their accounts. Which of the following project constr...
IT securityproject constraintstimeline impactsecurity breach - Question #779Project management concepts
A project team learns that potential remodeling on the production floor might occur during the execution phase of their project. The project team starts debating the different opti...
risk managementmitigationexecution phaserisk response - Question #780Project management concepts
Everyone on the team agrees with a change request, and the team proceeds with the implementation. Which of the following steps is missing from the identified process?
change controlformal approvalchange management processchange request - Question #781Project management concepts
Which of the following will MOST likely result in changes to the project plan?
change managementincident managementproject planrisk triggers - Question #782Project management concepts
Which of the following is primarily responsible for developing the timeline?
project rolesproject schedulertimelineresponsibility - Question #783Project management concepts
A project manager has established a series of virtual meetings with project team members in different parts of the world. Team members from one country almost never show up to the...
virtual teamstime zonescommunication managementglobal teams - Question #784Project management concepts
There is friction between team members who were on the team before a merger took place and those who transitioned during the merger. This situation is having an adverse effect on t...
conflict resolutionteam buildingorganizational changerelationship building - Question #785Tools and documentation
Which of the following indicators would help the project manager to determine the financial status of the project?
earned value managementEVfinancial statusproject performance metrics - Question #786Project management concepts
In a weak matrix, a highly skilled project team member has been using company equipment to view inappropriate content. Which of the following steps should the project manager take...
weak matrixorganizational structureacceptable use policyauthority - Question #787Tools and documentation
A procurement project manager presents the project status at a steering committee review. One of the defined risks is becoming an issue. The steering committee provides feedback an...
risk registerrisk managementissue logrisk identification - Question #788Project management concepts
The PMO is coordinating a series of interrelated functions to achieve a specific business goal. These functions require non-unique operational processes. Which of the following is...
program managementPMOportfolioorganizational structure - Question #789Project management concepts
A vendor notifies the project manager that the scheduled date for a deliverable on the critical path cannot be met due to a lack of resources. Which of the following are MOST likel...
critical pathvendor managementschedule changesrisk register updates - Question #790Project management concepts
A project team is working on a sensitive project that requires the use of an isolated email system for all project communications. Outside vendors are frustrated by the lack of res...
communication managementvendor communicationsensitive projectexternal communication - Question #791Project management concepts
A project manager is notified of a natural disaster that may occur during an active project's execution. Which of the following is the BEST option to maintain budget and scope?
risk mitigationbusiness continuitynatural disasterbudget protection - Question #792Project management concepts
A project team is analyzing the risk register and identifies several issues that may be related to potential instability of the accounting system. Which of the following should be...
risk responserisk registerroot cause analysissystem instability - Question #793Tools and documentation
Based on the information below: AC = 100 SV = 80 EV = 120 Which of the following is the CPI of the project?
CPIearned value managementcost performance indexEV formula - Question #794Tools and documentation
A vendor is not meeting the agreed-upon quality of deliverables. To try to renegotiate the contract with the vendor, which of the following documents should the project manager use...
SLAvendor managementcontract documentsquality management - Question #795Project management concepts
While creating the communication management plan, the project manager determines sharing the project's progress with the entire company would be beneficial. Which of the following...
communication managementcommunication methodsstakeholder communicationproject progress - Question #796Project management concepts
A meeting organizer is deciding high-level requirements, the business case, and funding for a new project. Which of the following is the meeting organizer?
project sponsorproject rolesbusiness caseproject initiation - Question #797Project management concepts
A project manager, who is overseeing a project in a functional environment, lost two project team members to other projects. The project manager does not anticipate getting any rep...
resource managementscope reductionfunctional organizationproject constraints - Question #798Project management concepts
A stakeholder tells the project manager that a vendor was verbally aggressive during a meeting. Since the project is almost completed, the project manager decides to log and close...
conflict resolutionforcingconflict management strategiesstakeholder management - Question #799Basics of IT and governance
A company is migrating its information technology activities to a cloud service provider. Which of the following BEST describes this course of action?
outsourcingcloud migrationIT governanceprocurement - Question #800Project management concepts
During a project, there has been a high turnover of resources provided by a third-party vendor. The project team claims the resources are unable to complete tasks in a timely manne...
interproject resource contentionvendor managementresource allocationthird-party resources