PK0-004 · Question #768
Given the status report excerpt below: Overall status: The project is tracking well. Tasks are being completed on time. Costs are lower than expected. Risk/issues are regularly being monitored are…
The correct answer is B. The project has experienced a risk trigger recently that may impact the project very soon. A vague risk/issues statement in an otherwise positive status report is a signal that a risk trigger may have recently occurred and is being actively watched.
Question
Given the status report excerpt below:
Overall status: The project is tracking well. Tasks are being completed on time. Costs are lower than expected. Risk/issues are regularly being monitored are tracked. Which of the following MOST likely is occurring in the project?
Options
- AThe project manager forgot to update the risks/issues status.
- BThe project has experienced a risk trigger recently that may impact the project very soon.
- CThere is nothing out of the ordinary; the project is progressing as expected.
- DThe project manager did not include any risks/issues detail because it is yellow and not red.
How the community answered
(30 responses)- A10% (3)
- B57% (17)
- C7% (2)
- D27% (8)
Why each option
A vague risk/issues statement in an otherwise positive status report is a signal that a risk trigger may have recently occurred and is being actively watched.
The PM clearly did not forget to address risks/issues - the update explicitly states they are being monitored and tracked, demonstrating awareness.
When a risk trigger occurs, a project manager may continue reporting healthy overall metrics while closely monitoring the developing situation. The generic phrase 'regularly being monitored and tracked' - with no specific green/yellow/red status - is a pattern that suggests something has been triggered and is under observation, rather than a clean 'no active issues' declaration.
The conspicuously vague risk/issues language, lacking any specific status detail, indicates something atypical is occurring rather than a routine healthy update.
A yellow status is typically flagged explicitly in a status report; the total absence of specific detail points to active monitoring of a triggered risk, not a simple yellow omission.
Concept tested: Risk trigger identification in project status reporting
Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok
Topics
Community Discussion
No community discussion yet for this question.