nerdexam
ExamsPK0-004Questions#769
CompTIA

PK0-004 · Question #769

PK0-004 Question #769: Real Exam Question with Answer & Explanation

The correct answer is A: Accept. Knowingly proceeding with a decision despite awareness of a potential negative consequence - without acting to prevent, reduce, or transfer it - is the definition of risk acceptance.

Question

A project manager decides to release a product one month later, knowing marketing studies have shown doing so could require increased manufacturing capacity. Which of the following risk strategies is being employed?

Options

  • AAccept
  • BExploit
  • CTransfer
  • DMitigate

Explanation

Knowingly proceeding with a decision despite awareness of a potential negative consequence - without acting to prevent, reduce, or transfer it - is the definition of risk acceptance.

Common mistakes.

  • B. Exploit is a response strategy reserved for positive risks (opportunities), used to ensure an upside is fully realized - it does not apply to negative risks like increased costs.
  • C. Transfer involves shifting the financial or operational burden of a risk to a third party (via insurance, contract, or outsourcing), which is not occurring here.
  • D. Mitigate requires taking action to reduce the probability or impact of the risk, but the PM makes no such effort - they simply proceed with full knowledge of the consequence.

Concept tested. Negative risk response strategy - acceptance

Reference. https://www.pmi.org/pmbok-guide-standards/foundational/pmbok

Community Discussion

No community discussion yet for this question.

Full PK0-004 Practice