nerdexam
CompTIA

PK0-004 · Question #769

A project manager decides to release a product one month later, knowing marketing studies have shown doing so could require increased manufacturing capacity. Which of the following risk strategies…

The correct answer is A. Accept. Knowingly proceeding with a decision despite awareness of a potential negative consequence - without acting to prevent, reduce, or transfer it - is the definition of risk acceptance.

Project management concepts

Question

A project manager decides to release a product one month later, knowing marketing studies have shown doing so could require increased manufacturing capacity. Which of the following risk strategies is being employed?

Options

  • AAccept
  • BExploit
  • CTransfer
  • DMitigate

How the community answered

(32 responses)
  • A
    81% (26)
  • B
    9% (3)
  • C
    3% (1)
  • D
    6% (2)

Why each option

Knowingly proceeding with a decision despite awareness of a potential negative consequence - without acting to prevent, reduce, or transfer it - is the definition of risk acceptance.

AAcceptCorrect

Risk acceptance means the project team acknowledges a risk and consciously decides to proceed without changing the plan to address it. The PM releases the product later while fully aware that increased manufacturing capacity may result, taking no steps to prevent or reduce that outcome - this is a deliberate, passive acceptance of the identified negative risk.

BExploit

Exploit is a response strategy reserved for positive risks (opportunities), used to ensure an upside is fully realized - it does not apply to negative risks like increased costs.

CTransfer

Transfer involves shifting the financial or operational burden of a risk to a third party (via insurance, contract, or outsourcing), which is not occurring here.

DMitigate

Mitigate requires taking action to reduce the probability or impact of the risk, but the PM makes no such effort - they simply proceed with full knowledge of the consequence.

Concept tested: Negative risk response strategy - acceptance

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok

Topics

#risk response strategies#accept#schedule risk#opportunity management

Community Discussion

No community discussion yet for this question.

Full PK0-004 Practice