PK0-004 · Question #788

The PMO is coordinating a series of interrelated functions to achieve a specific business goal. These functions require non-unique operational processes. Which of the following is the PMO organizing?

The correct answer is C. Program. A program is a group of related projects, subsidiary programs, and operational activities managed in a coordinated manner to achieve benefits and strategic goals not obtainable by managing them independently. The key indicators here are: (1) interrelated functions, (2) a…

Project management concepts

Question

The PMO is coordinating a series of interrelated functions to achieve a specific business goal. These functions require non-unique operational processes. Which of the following is the PMO organizing?

Options

  • ANetwork diagram
  • BProduct backlog
  • CProgram
  • DPortfolio

How the community answered

(28 responses)
  • A
    4% (1)
  • B
    4% (1)
  • C
    86% (24)
  • D
    7% (2)

Explanation

A program is a group of related projects, subsidiary programs, and operational activities managed in a coordinated manner to achieve benefits and strategic goals not obtainable by managing them independently. The key indicators here are: (1) interrelated functions, (2) a specific business goal, and (3) non-unique (repeatable) operational processes. This aligns with the definition of a program, which links related work toward a common outcome. A portfolio (D) is broader - it aligns all projects and programs to strategic objectives but does not require the functions to be interrelated. A product backlog (B) is an Agile artifact, and a network diagram (A) is a scheduling tool.

Topics

#program management#PMO#portfolio#organizational structure