PK0-004 · Question #789

PK0-004 Question #789: Real Exam Question with Answer & Explanation

The correct answer is C: Audits. When a critical-path deliverable is delayed, three immediate responses are triggered: (D) Schedule changes - a critical path delay directly extends the project end date, requiring the schedule to be revised. (G) Risk register updates - the vendor's resource shortage is either a n

Question

A vendor notifies the project manager that the scheduled date for a deliverable on the critical path cannot be met due to a lack of resources. Which of the following are MOST likely to be triggered? (Choose three.)

Options

  • AMilestones
  • BStakeholder changes
  • CAudits
  • DSchedule changes
  • EIncident response
  • FBusiness continuity response
  • GRisk register updates

Explanation

When a critical-path deliverable is delayed, three immediate responses are triggered: (D) Schedule changes - a critical path delay directly extends the project end date, requiring the schedule to be revised. (G) Risk register updates - the vendor's resource shortage is either a newly realized risk or confirms an existing one; either way, it must be logged and assessed in the risk register. (C) Audits - a vendor failing to meet a critical deliverable warrants a procurement/performance audit to assess compliance with the contract and identify corrective actions. Stakeholder changes (B) and business continuity response (F) are not directly triggered by a vendor resource issue. Milestones (A) may be affected but are outcomes of the schedule change, not independently triggered responses. Incident response (E) is typically reserved for security or safety events.