PK0-004 · Question #789
PK0-004 Question #789: Real Exam Question with Answer & Explanation
The correct answer is C: Audits. When a critical-path deliverable is delayed, three immediate responses are triggered: (D) Schedule changes - a critical path delay directly extends the project end date, requiring the schedule to be revised. (G) Risk register updates - the vendor's resource shortage is either a n
Question
Options
- AMilestones
- BStakeholder changes
- CAudits
- DSchedule changes
- EIncident response
- FBusiness continuity response
- GRisk register updates
Explanation
When a critical-path deliverable is delayed, three immediate responses are triggered: (D) Schedule changes - a critical path delay directly extends the project end date, requiring the schedule to be revised. (G) Risk register updates - the vendor's resource shortage is either a newly realized risk or confirms an existing one; either way, it must be logged and assessed in the risk register. (C) Audits - a vendor failing to meet a critical deliverable warrants a procurement/performance audit to assess compliance with the contract and identify corrective actions. Stakeholder changes (B) and business continuity response (F) are not directly triggered by a vendor resource issue. Milestones (A) may be affected but are outcomes of the schedule change, not independently triggered responses. Incident response (E) is typically reserved for security or safety events.
Community Discussion
No community discussion yet for this question.