PK0-004 · Question #787
A procurement project manager presents the project status at a steering committee review. One of the defined risks is becoming an issue. The steering committee provides feedback and agrees on a…
The correct answer is B. Update the risk register. When a new risk is identified, the immediate and mandatory first step is to document it in the risk register. The risk register is the authoritative repository for all project risks - capturing the risk description, probability, impact, and initial details before any analysis…
Question
A procurement project manager presents the project status at a steering committee review. One of the defined risks is becoming an issue. The steering committee provides feedback and agrees on a mitigation plan. After reviewing the meeting minutes and project documents, a new risk is created. Which of the following needs to occur FIRST?
Options
- AUpdate the issue log.
- BUpdate the risk register.
- CConduct a risk review meeting.
- DSubmit a change request to address the risk.
How the community answered
(38 responses)- A3% (1)
- B87% (33)
- C8% (3)
- D3% (1)
Explanation
When a new risk is identified, the immediate and mandatory first step is to document it in the risk register. The risk register is the authoritative repository for all project risks - capturing the risk description, probability, impact, and initial details before any analysis, response planning, or change requests occur. You cannot conduct a risk review meeting (C), submit a change request (D), or meaningfully update the issue log (A) for a new risk until it has been formally recorded. Documentation always precedes action in risk management.