nerdexam
ExamsPK0-004Questions#785
CompTIA

PK0-004 · Question #785

PK0-004 Question #785: Real Exam Question with Answer & Explanation

The correct answer is C: EV. Earned Value (EV) is the foundational metric in Earned Value Management (EVM) that represents the budgeted value of work actually completed to date. It is the core financial performance indicator because it translates physical progress into monetary terms, enabling meaningful com

Question

Which of the following indicators would help the project manager to determine the financial status of the project?

Options

  • ACV
  • BSV
  • CEV
  • DPV
  • ECOQ
  • FAC
  • GBAC

Explanation

Earned Value (EV) is the foundational metric in Earned Value Management (EVM) that represents the budgeted value of work actually completed to date. It is the core financial performance indicator because it translates physical progress into monetary terms, enabling meaningful comparison against what was planned (PV) and what was spent (AC). Without EV, you cannot calculate Cost Variance (CV = EV − AC) or the Cost Performance Index (CPI). While AC shows what has been spent and BAC shows the total budget, only EV captures the financial value of work accomplished - making it the primary indicator of true financial status.

Community Discussion

No community discussion yet for this question.

Full PK0-004 Practice