A meeting organizer is deciding high-level requirements, the business case, and funding for a new project. Which of the following is the meeting organizer?
The correct answer is C. Sponsor. The project sponsor is the individual or group who provides financial resources and high-level direction for the project. The sponsor is responsible for defining the business case, securing funding, and establishing high-level requirements before and during project initiation…
Question
A meeting organizer is deciding high-level requirements, the business case, and funding for a new project. Which of the following is the meeting organizer?
Options
- APMO
- BProject coordinator
- CSponsor
- DProject manager
How the community answered
(19 responses)- B5% (1)
- C95% (18)
Explanation
The project sponsor is the individual or group who provides financial resources and high-level direction for the project. The sponsor is responsible for defining the business case, securing funding, and establishing high-level requirements before and during project initiation. The PMO (A) provides governance and standards. The project coordinator (B) handles administrative tasks. The project manager (D) is responsible for planning and executing the project - but the sponsor owns the business justification and funding authority.