A project manager, who is overseeing a project in a functional environment, lost two project team members to other projects. The project manager does not anticipate getting any replacements for the…
The correct answer is D. Negotiate with the project sponsor to reduce the scope of the project. In spite of hiring incompetent and inefficient members, it is better to negotiate with the project sponsor to reduce the scope of the project to save the project's credibility.
Question
A project manager, who is overseeing a project in a functional environment, lost two project team members to other projects. The project manager does not anticipate getting any replacements for the remaining duration of the project. Which of the following would be the BEST solution to meet the project's timeline?
Options
- AAnnounce to project team members they will crash the project.
- BWork with stakeholders to reduce deliverable quality.
- CInform the organization's management there will be a delivery delay.
- DNegotiate with the project sponsor to reduce the scope of the project
How the community answered
(31 responses)- A6% (2)
- B13% (4)
- C29% (9)
- D52% (16)
Explanation
In spite of hiring incompetent and inefficient members, it is better to negotiate with the project sponsor to reduce the scope of the project to save the project's credibility.