nerdexam
CompTIA

PK0-004 · Question #797

A project manager, who is overseeing a project in a functional environment, lost two project team members to other projects. The project manager does not anticipate getting any replacements for the…

The correct answer is D. Negotiate with the project sponsor to reduce the scope of the project. In spite of hiring incompetent and inefficient members, it is better to negotiate with the project sponsor to reduce the scope of the project to save the project's credibility.

Project management concepts

Question

A project manager, who is overseeing a project in a functional environment, lost two project team members to other projects. The project manager does not anticipate getting any replacements for the remaining duration of the project. Which of the following would be the BEST solution to meet the project's timeline?

Options

  • AAnnounce to project team members they will crash the project.
  • BWork with stakeholders to reduce deliverable quality.
  • CInform the organization's management there will be a delivery delay.
  • DNegotiate with the project sponsor to reduce the scope of the project

How the community answered

(31 responses)
  • A
    6% (2)
  • B
    13% (4)
  • C
    29% (9)
  • D
    52% (16)

Explanation

In spite of hiring incompetent and inefficient members, it is better to negotiate with the project sponsor to reduce the scope of the project to save the project's credibility.

Topics

#resource management#scope reduction#functional organization#project constraints

Community Discussion

No community discussion yet for this question.

Full PK0-004 Practice