During a project, the purpose of examining the cost baseline is to:

The correct answer is C. anticipate the total planned costs. The cost baseline is the approved, time-phased budget used to measure project cost performance and represents all anticipated planned costs over the project lifecycle. It is not a tool for billing, minimum-cost analysis, or revenue comparison.

Tools and documentation

Question

During a project, the purpose of examining the cost baseline is to:

Options

  • Aorganize payment of the bills
  • Bdetermine the minimal cost of the project
  • Canticipate the total planned costs
  • Dcompare against the total planned income

How the community answered

(35 responses)
  • A
    3% (1)
  • B
    3% (1)
  • C
    91% (32)
  • D
    3% (1)

Why each option

The cost baseline is the approved, time-phased budget used to measure project cost performance and represents all anticipated planned costs over the project lifecycle. It is not a tool for billing, minimum-cost analysis, or revenue comparison.

Aorganize payment of the bills

Organizing payment of bills is an accounts payable or financial administration function, not the purpose of establishing or examining a cost baseline.

Bdetermine the minimal cost of the project

The cost baseline reflects planned costs derived from estimates and the schedule, not the minimum possible cost - cost optimization is a separate exercise from baselining.

Canticipate the total planned costsCorrect

The cost baseline aggregates all planned project expenditures into a time-phased budget, allowing the project manager to anticipate total planned costs at any point in the project. It serves as the reference point for earned value management, enabling comparisons between what was planned to spend and what was actually spent. Establishing the cost baseline essentially answers the question - how much do we expect to spend and when?

Dcompare against the total planned income

The cost baseline tracks planned expenditures (outflows only) - comparing against total planned income is a profitability or financial forecasting function, not a cost performance measurement function.

Concept tested: Project cost baseline purpose and cost performance measurement

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok