PK0-004 · Question #766

A project is due to deliver, configure, and install a collection of medical devices. The first device in the collection is reportedly four weeks behind schedule is manufacturing. Which of the…

The correct answer is B. Rearrange the installation dates since other devices are already on site. When one item in a sequential installation is delayed but others are already on site, reordering the installation schedule allows the team to continue productive work rather than waiting idle.

Project life cycle phases

Question

A project is due to deliver, configure, and install a collection of medical devices. The first device in the collection is reportedly four weeks behind schedule is manufacturing. Which of the following BEST describes how the project manager can keep the project on track?

Options

  • AExpedite shipping of the first item to keep the installation order.
  • BRearrange the installation dates since other devices are already on site.
  • CWhen the late equipment arrives, have the team work overtime.
  • DExplain the vendor payments will be withheld if delivery is not met.

How the community answered

(59 responses)
  • A
    3% (2)
  • B
    83% (49)
  • C
    5% (3)
  • D
    8% (5)

Why each option

When one item in a sequential installation is delayed but others are already on site, reordering the installation schedule allows the team to continue productive work rather than waiting idle.

AExpedite shipping of the first item to keep the installation order.

Expediting shipping cannot recover time lost in manufacturing, since the delay is four weeks behind in production, not in transit.

BRearrange the installation dates since other devices are already on site.Correct

Rearranging installation dates for devices already on site is a proactive schedule management technique that keeps the project moving forward by performing available work out of the originally planned order. This avoids a complete standstill caused by the delayed device and maximizes resource utilization while waiting for the late equipment to arrive.

CWhen the late equipment arrives, have the team work overtime.

Having the team work overtime only after the late equipment arrives does not keep the project on track during the current delay period.

DExplain the vendor payments will be withheld if delivery is not met.

Withholding vendor payments is a reactive contractual threat and does not address the immediate schedule impact or keep installation work progressing.

Concept tested: Schedule management - resequencing project activities

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok

Topics

#schedule management#delay response#installation reordering#vendor delay