PK0-004 · Question #765
Which of the following indicators will assist the project manager in determining the health of the budget?
The correct answer is B. CPI. This CPI can determine whether the project is under or over budget. The AC lets you know how much you have actually spent and the EV will let you know how much the project is actually worth. So the CPI would be the best indicator of whether the budget is healthy although the…
Question
Which of the following indicators will assist the project manager in determining the health of the budget?
Options
- ASV
- BCPI
- CAC
- DEV
- EETC
How the community answered
(16 responses)- A6% (1)
- B88% (14)
- D6% (1)
Explanation
This CPI can determine whether the project is under or over budget. The AC lets you know how much you have actually spent and the EV will let you know how much the project is actually worth. So the CPI would be the best indicator of whether the budget is healthy although the other two can be used as well.