PK0-004 · Question #793
Based on the information below: AC = 100 SV = 80 EV = 120 Which of the following is the CPI of the project?
The correct answer is C. 1.2. CPI (Cost Performance Index) measures cost efficiency and is calculated as EV ÷ AC (Earned Value divided by Actual Cost). Using the given values: CPI = 120 ÷ 100 = 1.2. A CPI greater than 1.0 means the project is under budget (getting more value than the money spent). Note: SV…
Question
Based on the information below:
AC = 100 SV = 80 EV = 120 Which of the following is the CPI of the project?
Options
- A0.8
- B0.83
- C1.2
- D1.25
How the community answered
(22 responses)- A14% (3)
- B9% (2)
- C73% (16)
- D5% (1)
Explanation
CPI (Cost Performance Index) measures cost efficiency and is calculated as EV ÷ AC (Earned Value divided by Actual Cost). Using the given values: CPI = 120 ÷ 100 = 1.2. A CPI greater than 1.0 means the project is under budget (getting more value than the money spent). Note: SV (Schedule Variance) = 80 is not needed for CPI calculation - it is a distractor. SV is used for schedule analysis, not cost efficiency.