Which of the following is primarily responsible for developing the timeline?
The correct answer is D. Project scheduler. The project scheduler is responsible for developing and maintaining the project schedule, communicating the timelines and due dates, reporting schedule performance, and communicating any schedule changes to the stakeholders and project team members.
Project management concepts
Question
Which of the following is primarily responsible for developing the timeline?
Options
- AProject sponsor
- BProject coordinator
- CProject manager
- DProject scheduler
How the community answered
(56 responses)- A4% (2)
- B2% (1)
- C2% (1)
- D93% (52)
Explanation
The project scheduler is responsible for developing and maintaining the project schedule, communicating the timelines and due dates, reporting schedule performance, and communicating any schedule changes to the stakeholders and project team members.