A project manager is notified of a natural disaster that may occur during an active project's execution. Which of the following is the BEST option to maintain budget and scope?
The correct answer is A. Contract a business continuity firm to provide for relocation. A contracted business continuity firm enhances maintaining the budget and scope of activities while relocating in case of any natural disaster.
Project management concepts
Question
A project manager is notified of a natural disaster that may occur during an active project's execution. Which of the following is the BEST option to maintain budget and scope?
Options
- AContract a business continuity firm to provide for relocation.
- BAccept that the disaster may alter deliverable quality.
- CSecure an insurance policy in the even) a disaster occurs.
- DBuild lag into the schedule to accommodate average time lost.
How the community answered
(63 responses)- A56% (35)
- B6% (4)
- C25% (16)
- D13% (8)
Explanation
A contracted business continuity firm enhances maintaining the budget and scope of activities while relocating in case of any natural disaster.
Topics
#risk mitigation#business continuity#natural disaster#budget protection