The correct answer is A: Contract a business continuity firm to provide for relocation.. A contracted business continuity firm enhances maintaining the budget and scope of activities while relocating in case of any natural disaster.

Question

A project manager is notified of a natural disaster that may occur during an active project's execution. Which of the following is the BEST option to maintain budget and scope?

Options

  • AContract a business continuity firm to provide for relocation.
  • BAccept that the disaster may alter deliverable quality.
  • CSecure an insurance policy in the even) a disaster occurs.
  • DBuild lag into the schedule to accommodate average time lost.

Explanation

A contracted business continuity firm enhances maintaining the budget and scope of activities while relocating in case of any natural disaster.