A project manager realizes there is a significant risk event. Which of the following is the FIRST step the project manager should perform?

The correct answer is D. Activate the contingency plan. If the risk is significant we should activate the contingency plan.

Project management concepts

Question

A project manager realizes there is a significant risk event. Which of the following is the FIRST step the project manager should perform?

Options

  • AEscalate the issue to the sponsor
  • BAssign an owner to take action
  • CUpdate the issue log
  • DActivate the contingency plan

How the community answered

(36 responses)
  • A
    8% (3)
  • B
    14% (5)
  • C
    6% (2)
  • D
    72% (26)

Explanation

If the risk is significant we should activate the contingency plan.

Topics

#risk management#contingency plan#risk response#risk events