nerdexam
CompTIA

PK0-004 · Question #752

The responsibility of estimating how long a task will take belongs to the:

The correct answer is B. project team. Task duration estimates should come from the project team members who will perform the work, as they have the hands-on expertise required to provide accurate estimates.

Project management concepts

Question

The responsibility of estimating how long a task will take belongs to the:

Options

  • Aproject scheduler
  • Bproject team
  • Cproject manager
  • Dproject coordinator

How the community answered

(58 responses)
  • A
    5% (3)
  • B
    91% (53)
  • C
    2% (1)
  • D
    2% (1)

Why each option

Task duration estimates should come from the project team members who will perform the work, as they have the hands-on expertise required to provide accurate estimates.

Aproject scheduler

A project scheduler organizes and maintains the schedule tool and timeline but relies on the team's input for duration estimates rather than generating them independently.

Bproject teamCorrect

The project team is responsible for estimating task durations because team members have direct technical knowledge of the work involved. This bottom-up estimating approach leverages subject matter expertise, producing more reliable estimates than those generated by managers who may not perform the work themselves.

Cproject manager

The project manager facilitates and oversees the estimating process but delegates the actual estimation to team members who understand the technical effort required.

Dproject coordinator

A project coordinator handles administrative and logistical tasks and does not have the technical authority or expertise to estimate task durations.

Concept tested: Role of the project team in duration estimating

Source: https://www.pmi.org/learning/library/estimate-activity-durations-project-management-6168

Topics

#task estimation#project team#roles and responsibilities#duration estimating

Community Discussion

No community discussion yet for this question.

Full PK0-004 Practice