PK0-004 · Question #752
The responsibility of estimating how long a task will take belongs to the:
The correct answer is B. project team. Task duration estimates should come from the project team members who will perform the work, as they have the hands-on expertise required to provide accurate estimates.
Question
The responsibility of estimating how long a task will take belongs to the:
Options
- Aproject scheduler
- Bproject team
- Cproject manager
- Dproject coordinator
How the community answered
(58 responses)- A5% (3)
- B91% (53)
- C2% (1)
- D2% (1)
Why each option
Task duration estimates should come from the project team members who will perform the work, as they have the hands-on expertise required to provide accurate estimates.
A project scheduler organizes and maintains the schedule tool and timeline but relies on the team's input for duration estimates rather than generating them independently.
The project team is responsible for estimating task durations because team members have direct technical knowledge of the work involved. This bottom-up estimating approach leverages subject matter expertise, producing more reliable estimates than those generated by managers who may not perform the work themselves.
The project manager facilitates and oversees the estimating process but delegates the actual estimation to team members who understand the technical effort required.
A project coordinator handles administrative and logistical tasks and does not have the technical authority or expertise to estimate task durations.
Concept tested: Role of the project team in duration estimating
Source: https://www.pmi.org/learning/library/estimate-activity-durations-project-management-6168