- Question #51Project Budgeting
Your customer has implemented budgeting for projects. The current budget of their projects has been changed several times. Therefore they want to get an overviews of the budget upd...
budget reportinghierarchical reportbudget updatesline item report - Question #52Project Planning
Which of the following is used to plan basic dates manually for WBS elements? Choose the correct answers. There are 2 correct answers to this question.
basic datesWBS element schedulingProject Builderproject planning board - Question #53Project Budgeting
You have assigned a budget to WBS element with your project What budget function could be used to check assigned values against the current budget?
availability controlbudget checkassigned valuesWBS element - Question #54Project Planning
How are capacity requirements determined?
capacity requirementscontrol keyschedulingcapacity determination - Question #55Project Execution
Your customer uses Progress Tracking for network components and mantains dates of events manually. They need to implement scheduling of events. What is the requisites for implement...
progress trackingevent schedulingevent scenariosnetwork components - Question #56Materials in Project Systems
You want to create purchase requisition for the material used in your project. However after releasing the project, no purchase requisition has been created. What could be the reas...
purchase requisitionprocurement typeitem categorymaterial number - Question #57Project Planning
Your costumer Project/planning Board to create/update Gant charts. Which the following are characteristics of the Project Planning Board. Note: there are 3 correct answers for this...
project planning boardGantt chartproduction orderscolor management - Question #58Project Structures
You want to enable user fields for customer project. Therefore you create several field keys. What is the benefit of assigning a field key to the project profile?
user fieldsfield keyproject profileWBS element - Question #59Project Planning
How are earliest dates and latest dates of activities schedule?
forward schedulingbackward schedulingearliest dateslatest dates - Question #60Project Structures
A customer works in a multinivel production environment with bill of material and routing. To avoid unnecessary stock cost , they do not want to produce.. Which setup do you recomm...
multilevel productionsales orderproject hierarchyBOM routing - Question #61Project Planning
You intent to work with predefined project coding mask to create project definitions. What do you have to consider?
project coding maskproject definitionproject numberingWBS coding - Question #62Costs and Revenues in Project Systems
A customer wants to allocate overhead rates to a WBS element. What must you assign to the WBS element?
overhead ratescosting sheetWBS elementoverhead allocation - Question #63Materials in Project Systems
How can the system activate requirements (such as reservations or purchase requisitions)? Note: There are 2 correct answers to this question
reservationspurchase requisitionsnetwork releaseproject activation - Question #64Project Structures
You use a WBS project structure with network and maintenance order. You want to schedule both the network and the maintenance order . What do you have to consider?
WBS structurenetwork schedulingmaintenance orderproject scheduling - Question #65Period-End Closing
A customer use cross- company - code project with a top billing element and additional billing element underneath (por debajo) for each company code. Although the internal .. corre...
cross-company-coderesults analysisbilling elementvaluation method - Question #66Project Execution
You are using assembly processing. You need to determine the delivery date of a sales order item with an account assignment to the project. What are the prerequisites? Note: There...
assembly processingsales orderstandard networkmaterial master - Question #67Project Execution
You plan double the work on each internal activity for multiple project. What do you recommend?
mass changeinternal activitiesCNMASSproject builder - Question #68Project Execution
You are using network and internal activities in your project . You have already create a purchase requisition and the bid invitation.,and have entered the quotation ... What is th...
external processingpurchase ordervendor selectionservice entry sheet - Question #69Project Planning
The__________________that you specify when you create a project definition is unique for the entire project. Choose the correct answer.
project definitioncontrolling areaorganizational unitsproject creation - Question #70Project Budgeting
A service Company use project management and they complain that the system does not prevent their project manager from exceeding their budget. What action do you have tsolve the pr...
availability controlbudget profiletolerance limitsbudget overrun - Question #71Project Planning
You have a project with a network, material and milestone. You want to plan an activity to start two days after its predecessor. How can you do that? Note: there are 2 correct answ...
activity relationshipsoffsetscheduling constraintsnetwork scheduling - Question #72Project Execution
You want to exchange data between SAP Project System and Microsoft What interface do you use?
EPS interfaceMicrosoft Projectdata exchangeexternal integration - Question #73Costs and Revenues in Project Systems
Which of the following transactions can you use to post actual cost for external processing. Note: there are 2 correct answer for this question.
actual costsexternal processingservice entry sheetgoods receipt - Question #74Project Structures
Which of the following statements are true? Choose the correct answers. There are 2 correct answers to this question.
WBSnetworkproject structureactivity-based project - Question #75Project Structures
Which statement regarding the creation of a new work breakdown structure (WBS element) are true? Note: there are 3 correct answer for this question.
WBS elementbilling elementplanning elementaccount assignment - Question #76Project Structures
How can you define external task in your project. Note: there are 2 correct answers for this question.
external activityservice activitynetworkexternal processing - Question #77Project Structures
Which the following statement regarding networks are correct?. Note: there are 3 correct answers for this question.
network activitieswork centercapacity requirementsactivity elements - Question #78Project Budgeting
When using budgeting and active availability control, which business transactions affect the current budget?
availability controlcurrent budgetsupplementsbudget transfers - Question #79Project Planning
You have created a network with successive activities. After scheduling the network, the Gantt chart shows that every activity has the same earliest start and earliest finish date...
network schedulingactivity durationGantt chartscheduling diagnosis - Question #80Materials in Project Systems
How can material components be assigned to network activities?
material componentsnetwork activitiesBOM transfercatalog assignment - Question #81Materials in Project Systems
What are valid procurement types for stock items? Note: There are 3 correct answers to this question
procurement typesstock itemspurchase requisitionplanned order - Question #82Materials in Project Systems
Which objects do you have to maintain to enable automatic assignment of material components to the project? Note: There are 2 correct answers to this question
material componentsautomatic assignmentBOM itemmaterial master - Question #83Project Execution
When you create a service activity in your network, what data can be entered? Note: There are 3 correct answers to this question.
service activityservice specificationoverall limitvendor - Question #84Project Planning
Float time is calculated during scheduling. Which of the following statements about float time are correct? Note: There are 3 correct answers to this question
float timeschedulingcritical pathWBS elements - Question #85Costs and Revenues in Project Systems
You have created an internally-processed network activity, and assigned a work center and the work. After saving, you discover that no planned costs are displayed in the cost eleme...
planned costswork center formulaactivity type pricingintegrated planning - Question #86Project Structures
What are some of the possible functions in user status profiles? Note: There are 2 correct answers to this question.
user statusstatus profilesbusiness transactionssystem status - Question #87Costs and Revenues in Project Systems
Which of the following business processes do NOT lead to the booking of actual costs to an object? Note: There are2 correct answers to this question
actual costsgoods receiptunvaluated project stocknon-stock items - Question #88Costs and Revenues in Project Systems
For which objects can billing plans be created? Note: There are 2 correct answers to this question
billing plansWBS elementssales order itemsrevenue planning - Question #89Materials in Project Systems
Your customer wants to use requirements grouping in SAP Project System. What are the prerequisites for requirements grouping of materials? Note: There are 2 correct answers to this...
requirements groupingproject stockMRP grouplot size procedure - Question #90Project Planning
You use networks and internal activities in your project. You have activated capacity requirements and notice that one work center is overloaded. You have no authorization to chang...
capacity levelingwork center overloadproject planning boardscheduling - Question #91Project Reporting
A customer needs to analyze the capacity requirements of their network activities. Which reports do you recommend? Note: There are 2 correct answers to this question
capacity reportsresource reportshierarchical reportsnetwork activities - Question #92Project Execution
You are using WBS elements and activities are NOT assigned. Which statements apply to the maintenance of the actual start and finish? Note: There are 2 correct answers to this ques...
actual datesWBS elementsproject statusactual start finish - Question #93Period-End Closing
What functions are available for period end closing in SAP Project System? Note: There are 3 correct answers to this question
settlementresults analysisprogress analysisperiod end closing - Question #94Project Planning
You have created a network with planned work for internal activities. In a capacity planning report, you discover that no capacity requirements were determined. What are the possib...
capacity requirementswork centernetwork activitycapacity indicator - Question #95Project Execution
You want to confirm working hours to a WBS element using SAP Cross Application Time Sheet (SAP CATS). However, an error message occurs. What could be the reason?
CATStime sheet confirmationWBS elementsystem status - Question #96Project Planning
What is copied when transferring a simulation version back to an operative project?
simulation versionoperative projectWBS elementsnetwork activities - Question #97Project Execution
You want to set up the field selection of the Cross-Application Time Sheet (CATS) in Customizing. Which influencing field do you use?
CATSdata entry profilefield selectionCustomizing - Question #98Project Budgeting
You have assigned a budget to WBS elements within your project. What function can be used to check assigned values against the current budget
availability controlbudgetWBS elementsassigned values - Question #99Project Budgeting
A service company uses project management and they complain that the system does not prevent their project managers from exceeding their budgets. What actions do you have to take t...
availability controlbudget profiletolerance limitsbudget overrun prevention - Question #100Materials in Project Systems
You have assigned a material to a network activity and want to determine the requirement date related to this activity. What set of dates do you have to maintain?
requirement datenetwork activitybasic datesmaterial assignment