- Question #51
Your customer has implemented budgeting for projects. The current budget of their projects has been changed several times. Therefore they want to get an overviews of the budget upd...
- Question #52
Which of the following is used to plan basic dates manually for WBS elements? Choose the correct answers. There are 2 correct answers to this question.
- Question #53
You have assigned a budget to WBS element with your project What budget function could be used to check assigned values against the current budget?
- Question #54
How are capacity requirements determined?
- Question #55
Your customer uses Progress Tracking for network components and mantains dates of events manually. They need to implement scheduling of events. What is the requisites for implement...
- Question #56
You want to create purchase requisition for the material used in your project. However after releasing the project, no purchase requisition has been created. What could be the reas...
- Question #57
Your costumer Project/planning Board to create/update Gant charts. Which the following are characteristics of the Project Planning Board. Note: there are 3 correct answers for this...
- Question #58
You want to enable user fields for customer project. Therefore you create several field keys. What is the benefit of assigning a field key to the project profile?
- Question #59
How are earliest dates and latest dates of activities schedule?
- Question #60
A customer works in a multinivel production environment with bill of material and routing. To avoid unnecessary stock cost , they do not want to produce.. Which setup do you recomm...
- Question #61
You intent to work with predefined project coding mask to create project definitions. What do you have to consider?
- Question #62
A customer wants to allocate overhead rates to a WBS element. What must you assign to the WBS element?
- Question #63
How can the system activate requirements (such as reservations or purchase requisitions)? Note: There are 2 correct answers to this question
- Question #64
You use a WBS project structure with network and maintenance order. You want to schedule both the network and the maintenance order . What do you have to consider?
- Question #65
A customer use cross- company - code project with a top billing element and additional billing element underneath (por debajo) for each company code. Although the internal .. corre...
- Question #66
You are using assembly processing. You need to determine the delivery date of a sales order item with an account assignment to the project. What are the prerequisites? Note: There...
- Question #67
You plan double the work on each internal activity for multiple project. What do you recommend?
- Question #68
You are using network and internal activities in your project . You have already create a purchase requisition and the bid invitation.,and have entered the quotation ... What is th...
- Question #69
The__________________that you specify when you create a project definition is unique for the entire project. Choose the correct answer.
- Question #70
A service Company use project management and they complain that the system does not prevent their project manager from exceeding their budget. What action do you have tsolve the pr...
- Question #71
You have a project with a network, material and milestone. You want to plan an activity to start two days after its predecessor. How can you do that? Note: there are 2 correct answ...
- Question #72
You want to exchange data between SAP Project System and Microsoft What interface do you use?
- Question #73
Which of the following transactions can you use to post actual cost for external processing. Note: there are 2 correct answer for this question.
- Question #74
Which of the following statements are true? Choose the correct answers. There are 2 correct answers to this question.
- Question #75
Which statement regarding the creation of a new work breakdown structure (WBS element) are true? Note: there are 3 correct answer for this question.
- Question #76
How can you define external task in your project. Note: there are 2 correct answers for this question.
- Question #77
Which the following statement regarding networks are correct?. Note: there are 3 correct answers for this question.
- Question #78
When using budgeting and active availability control, which business transactions affect the current budget?
- Question #79
You have created a network with successive activities. After scheduling the network, the Gantt chart shows that every activity has the same earliest start and earliest finish date...
- Question #80
How can material components be assigned to network activities?
- Question #81
What are valid procurement types for stock items? Note: There are 3 correct answers to this question
- Question #82
Which objects do you have to maintain to enable automatic assignment of material components to the project? Note: There are 2 correct answers to this question
- Question #83
When you create a service activity in your network, what data can be entered? Note: There are 3 correct answers to this question.
- Question #84
Float time is calculated during scheduling. Which of the following statements about float time are correct? Note: There are 3 correct answers to this question
- Question #85
You have created an internally-processed network activity, and assigned a work center and the work. After saving, you discover that no planned costs are displayed in the cost eleme...
- Question #86
What are some of the possible functions in user status profiles? Note: There are 2 correct answers to this question.
- Question #87
Which of the following business processes do NOT lead to the booking of actual costs to an object? Note: There are2 correct answers to this question
- Question #88
For which objects can billing plans be created? Note: There are 2 correct answers to this question
- Question #89
Your customer wants to use requirements grouping in SAP Project System. What are the prerequisites for requirements grouping of materials? Note: There are 2 correct answers to this...
- Question #90
You use networks and internal activities in your project. You have activated capacity requirements and notice that one work center is overloaded. You have no authorization to chang...
- Question #91
A customer needs to analyze the capacity requirements of their network activities. Which reports do you recommend? Note: There are 2 correct answers to this question
- Question #92
You are using WBS elements and activities are NOT assigned. Which statements apply to the maintenance of the actual start and finish? Note: There are 2 correct answers to this ques...
- Question #93
What functions are available for period end closing in SAP Project System? Note: There are 3 correct answers to this question
- Question #94
You have created a network with planned work for internal activities. In a capacity planning report, you discover that no capacity requirements were determined. What are the possib...
- Question #95
You want to confirm working hours to a WBS element using SAP Cross Application Time Sheet (SAP CATS). However, an error message occurs. What could be the reason?
- Question #96
What is copied when transferring a simulation version back to an operative project?
- Question #97
You want to set up the field selection of the Cross-Application Time Sheet (CATS) in Customizing. Which influencing field do you use?
- Question #98
You have assigned a budget to WBS elements within your project. What function can be used to check assigned values against the current budget
- Question #99
A service company uses project management and they complain that the system does not prevent their project managers from exceeding their budgets. What actions do you have to take t...
- Question #100
You have assigned a material to a network activity and want to determine the requirement date related to this activity. What set of dates do you have to maintain?