C_TS412_2021 · Question #77

C_TS412_2021 Question #77: Real Exam Question with Answer & Explanation

The correct answer is B. You can assign more than one activity element to a network activity. C. Capacity requirements of a network activity are reduced when the activity is confirmed. E. You can assign the same work center to more than one activity on the same network.. "You can assign more than one activity element to a network activity." According to SAP Help Portal, "Capacity requirements of a network activity are reduced when the activity is confirmed." According to SAP Press4, "You can assign the same work center to more than one activity o

Question

Which the following statement regarding networks are correct?. Note: there are 3 correct answers for this question.

Options

  • AIf a network activity requires more capacity than available in a work center, the system
  • BYou can assign more than one activity element to a network activity.
  • CCapacity requirements of a network activity are reduced when the activity is confirmed.
  • DDuring scheduling, the system plans the network activities in such a way that the assigned work
  • EYou can assign the same work center to more than one activity on the same network.

Explanation

"You can assign more than one activity element to a network activity." According to SAP Help Portal, "Capacity requirements of a network activity are reduced when the activity is confirmed." According to SAP Press4, "You can assign the same work center to more than one activity on the

Community Discussion

No community discussion yet for this question.