C_TS412_2021 · Question #76
How can you define external task in your project. Note: there are 2 correct answers for this question.
The correct answer is B. Create an external activity in a network. D. Create a service activity in a network. "You can create external activities in a network to represent tasks that are performed by external service providers or vendors." According to SAP Press4, "You can create service activities in a network to represent tasks that are performed by internal service providers."
Question
How can you define external task in your project. Note: there are 2 correct answers for this question.
Options
- AAssign a purchase order for external processing to the project definition.
- BCreate an external activity in a network.
- CCreate a service milestone.
- DCreate a service activity in a network.
How the community answered
(55 responses)- A9% (5)
- B87% (48)
- C4% (2)
Explanation
"You can create external activities in a network to represent tasks that are performed by external service providers or vendors." According to SAP Press4, "You can create service activities in a network to represent tasks that are performed by internal service providers."